Structure Stabilization process:
1- Remove weather board at first and second floor plate.
2- install two layers of 1/2 plywood.
3- install 3/4 threaded rod through both walls using joist bays.

Structure Stabilization process:
1- Remove weather board at first and second floor plate.
2- install two layers of 1/2 plywood.
3- install 3/4 threaded rod through both walls using joist bays.